Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 19 | 19 | 19 | 0 |
16W663 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : उत्तराखण्ड शासन लोक निर्माण अनुभाग-2 देहरादून के पत्रांक- ......./।।।(2)/23-01(प्रा0आ0)/2023 दि0.14.11.2023
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
70.01
Resanction Cost :
70.01
Tentative Cost :
70.01
Exp. Upto Last Fy : 37.29
For CFY 2024-2025
Remaining : 32.72
Demand : 32.72
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 37.29
Work completed
Physical Progress:
At start of FY 2024-2025 : 2 %
Up to Date : 100 %
Sanction on :
8 months 3 days ago
14 Nov 2023
Tentative Completion date:
3 weeks 1 day ago
25 Jun 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण। दायित्व शेष। -- as on 02-Jul-2024
Physical Peramenters