Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 23 | 23 | 23 | 0 |
16W664 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : उत्तराखण्ड शासन लोक निर्माण अनुभाग-2 देहरादून के पत्रांक- ......./।।।(2)/23-01(प्रा0आ0)/2023 दि0.14.11.2023
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
111.63
Resanction Cost :
111.63
Tentative Cost :
111.63
Exp. Upto Last Fy : 86.74
For CFY 2024-2025
Remaining : 24.89
Demand : 24.89
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 86.74
Construction Started
Physical Progress:
At start of FY 2024-2025 : 4 %
Up to Date : 100 %
Sanction on :
8 months 3 days ago
14 Nov 2023
Tentative Completion date:
2 months 3 days ago
14 May 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण। दायित्व शेष। -- as on 06-Jun-2024
Physical Peramenters