Work Profile

17W122 :

No Pic Avilable Time series Gantt
मा0मु0मं0जी की घोषणा टनकपुर झूलाघाट मोटर मार्ग (अस्कोट प्रभाग) के अवशेष मार्ग का नवनिर्माण


Work not linked with IM

Bridges on The Basis of AI:

Administrative Approval Detail : 1541/।।।(2)/09-22(मा.मु.म.घो.)/10 दिनांक 31.3.2010

TS Amount (lakhs) : 351.65 Lacs

Financial Detail (in Rs Lakhs)

Sanction Cost :

351.65

Resanction Cost :

351.65

Tentative Cost :

351.65

Exp. Upto Last Fy : 334.85

For CFY 2024-2025

Remaining : 16.80

Demand : 16.80

Allotment : 0.00

Exp in CFY : 7.94

Total Up to Date Exp : 342.79

Construction Started

Physical Progress:

At start of FY 2024-2025 : 60 %

Up to Date : 60 %

Sanction on :
14 years 3 months ago
31 Mar 2010


Tentative Completion date:
3 years 3 months ago
31 Mar 2021


Actual Completion Date:
Not Yet Reported


Rating : 97

Remark

Bottelneck: no issue


कार्य पूर्ण, दायित्व शेष। -- as on 03-Jan-2024

Physical Peramenters

Particulars Sanction Resanction Upto Last Fy For Cfy 2024-2025
Remaining Target Achievement
Length of Road [Km] 7.8 6.5 6.5 0
No of Bridges 1 1 1 0
Span of Bridges [m] 25 25 25 0