Work Profile Report [17W138]

जनपद पिथौरागढ़ के विधानसभा क्षेत्र धारचूला के अन्तर्गत घट्टा बगड़ से सन्याल गांव मोटर मार्ग का निर्माण
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Forest
  • Remarks
  • Tenders

    Aggrements

    Project Activities

    alerts

    Documents

    Samples

Administrative Approval Detail : शा0स. 1472/।।।(2)/15-09(प्रा0आ0)/2014 दिनांक 23.3.2015

TS Amount (lakhs) : 0 Lacs

Budget Financial Head : State Sector ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

52.38

Resanction Cost :

52.38

Tentative Cost :

52.38

Exp. Upto Last Fy :

1.13

For CFY 2024-2025

Remaining :

51.25

Demand :

0.50

Allotment :

1.00

Exp in CFY :

0.00

Total Up to Date Exp :

1.13

Alignment Approved

Sanction on : 10 years 6 months ago

26 May 2014

Physical Progress:

At start of FY 2024-2025 :

0 %

Up to Date :

0 %

Tentative Completion date on :

Yet To Decide

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2024-2025
Remaining
Target
Achievement
Road [Km]
6
6
6
-

Remark

view all

क्षतिपूरक वृक्षारोपण हेतु इस कार्यालय प० सं० 2147 /13सी० दि० 05 .10 .2023 द्वारा तहसीलदार बंगापानी को पत्र प्रेषित किया गया था । आतिथि तक क्षतिपूरक वृक्षारोपण हेतु 7 .90 है० भूमि उपलब्ध नहीं कराई गयी। जिस कारण वनभूमि हस्तांतरण प्रस्ताव में अग्रिम कारवाही करना संभव नहीं हो पा रहा है। इस सम्बन्ध में इस कार्यालय प० सं० 582 /13सी० दि० 15 .05 .2024 द्वारा क्षतिपूरक वृक्षारोपण हेतु उपलब्ध कराने हेतु जिलाधिकारी पिथौरागढ़ को प्रेषित किया गया है । पुनः इस कार्यालय के पत्रांक 798 /13सी दि0 02 .07 .2024 द्वारा जिलाधिकारी पिथौरागढ़ को प्रेषित किया गया है। -- as on 23-Oct-2024

Rating : 2

Forest Case Pending At : 03: DM

Hindrance / Bottleneck : Long Term Forest Approval

Assets :

Work not linked with IM

Bridges on The Basis of AI: