Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3 | 3 | 3 | 0 | ||
No of Bridges | 1 | 1 | 1 | 0 | ||
Span of Bridges [m] | 21 | 21 | 21 | 0 |
17W193 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0 सं0 2062/(1)/।।।(2)/13-56 (प्रा0आ0)/2012 दिनांक 20-3-2013
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
39.06
Resanction Cost :
39.06
Tentative Cost :
39.06
Exp. Upto Last Fy : 16.88
For CFY 2024-2025
Remaining : 22.18
Demand : 22.18
Allotment : 0.00
Exp in CFY : 0.08
Total Up to Date Exp : 16.96
Work completed
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
11 years 3 months ago
20 Mar 2013
Tentative Completion date:
Yet To Decide
Actual Completion Date:
2 years 3 months ago
31 Mar 2022
Remark
Forest Status 21: Final
Bottelneck: no issue
कार्य पूर्ण, मुआवजा भुगतान की कार्यवाही की जा रही है। -- as on 07-Feb-2024
Physical Peramenters