Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2 | 2 | 2 | 0 | ||
No of Bridges | 1 | 1 | 1 | 0 | ||
Span of Bridges [m] | 12 | 12 | 12 | 0 |
17W194 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0 सं0 2062/(1)/।।।(2)/13-56 (प्रा0आ0)/2012 दिनांक 20-3-2013, पुनः शा0सं0 7215/।।।(2)/15-56(प्रा0आ0)/2012 दिनांके 31-12-2015
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
25.92
Resanction Cost :
25.92
Tentative Cost :
25.92
Exp. Upto Last Fy : 13.77
For CFY 2024-2025
Remaining : 12.15
Demand : 12.15
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 13.77
Work completed
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
11 years 3 months ago
20 Mar 2013
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 17: AIP Govt of India
Bottelneck: no issue
कार्य पूर्ण मुआवजा भुगतान शेष -- as on 17-Apr-2023
Physical Peramenters