Work Profile Report [17W239]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा0 सं0 428/।।।(2)/16-14 (मु0मं0घो0)/ 2015 दिनांक 23-01-2016
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
46.30
Resanction Cost :
46.30
Tentative Cost :
46.30
Exp. Upto Last Fy :
2.47
For CFY 2024-2025
Remaining :
43.83
Demand :
2.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
2.47
Alignment Approved
Sanction on : 8 years 11 months ago
23 Jan 2016
Physical Progress:
At start of FY 2024-2025 :
0 %
Up to Date :
0 %
Tentative Completion date on :
Yet To Decide
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
दिनांक 28.02.2024 को आपत्तियों का निराकरण कर नोडल स्तर पर विचााराधीन। -- as on 23-Oct-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand