Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2 | 2 | 2 | 0 | ||
Span of Bridges [m] | 100 | 100 | 100 | 0 |
17W251 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0 सं0 4594/।।।(2)/19-42(एम0एल0ए0)/ 2017 टी0सी0 दिनांक 27-12-2019
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
30.17
Resanction Cost :
30.17
Tentative Cost :
30.17
Exp. Upto Last Fy : 9.00
For CFY 2024-2025
Remaining : 21.17
Demand : 4.50
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 9.00
Unstarted Work
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
4 years 6 months ago
27 Dec 2019
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
पुल का स्थल चयन दिनांक 14.06.2023 को किया जा चुका है। समरेखन प्रस्ताव इस कार्यालय के पत्रांक 1025/4ए0सी0 दिनांक 16.06.2023 द्वारा अधीक्षण अभियन्ता तृतीय वृत्त लो0नि0वि0 पिथौरागढ़ को प्रेषित। -- as on 04-Aug-2023
Physical Peramenters