Work Profile Report [17W258]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा0सं0 428/।।।(2)/16-14 (मु0मं0घो0)/2015 दिनांक 23 जनवरी, 2016
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
98.27
Resanction Cost :
98.27
Tentative Cost :
98.27
Exp. Upto Last Fy :
1.90
For CFY 2025-2026
Remaining :
96.37
Demand :
0.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
1.90
Alignment Approved
Sanction on : 9 years 11 months ago
23 Jan 2016
Physical Progress:
At start of FY 2025-2026 :
35 %
Up to Date :
35 %
Tentative Completion date on : 1 year 2 months from now
31 Mar 2027
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
नोडल अधिकारी के पत्रांक 238/12 -1 दिनांक 23.06.2025 के द्वारा अनुपालन आख्या उप वन महानिदेशक भारत सरकार के स्तर में विचाराधीन। -- as on 01-Dec-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: