Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 14 | 14 | 14 | 0 |
17W27 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 1110/।।।(2)/14-52(प्रा0आ0)/2013 दिनांक 20-02-2014
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
81.90
Resanction Cost :
81.90
Tentative Cost :
81.90
Exp. Upto Last Fy : 67.63
For CFY 2024-2025
Remaining : 14.27
Demand : 14.27
Allotment : 0.00
Exp in CFY : 1.69
Total Up to Date Exp : 69.32
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
10 years 4 months ago
20 Feb 2014
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण मुआवजा प्रस्ताव गठित कर भुगतान किया जाना है -- as on 25-May-2023
Physical Peramenters