Work Profile Report [17W319]
Tenders
Project Activities
alerts
Samples
Administrative Approval Detail : शा0सं0 2120/।।।(2)/22-49(प्रा0आ0)/2018
TS Amount (lakhs) : 3298.4 Lacs
Budget Financial Head : NABARD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
3298.40
Resanction Cost :
3298.40
Tentative Cost :
3280.59
Saving
17.81
Exp. Upto Last Fy :
3,157.41
For CFY 2025-2026
Remaining :
140.99
Demand :
99.26
Allotment :
64.52
Exp in CFY :
64.52
Total Up to Date Exp :
3,221.93
Construction Started
Sanction on : 3 years 7 months ago
09 Jun 2022
Physical Progress:
At start of FY 2025-2026 :
95 %
Up to Date :
99 %
Tentative Completion date on : 1 week 15 hours from now
31 Jan 2026
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
स्वीकृत लागत के सापेक्ष्य गठित अनुबंध में बचत होने के कारण कार्य में बचत दर्शायी गयी है | -- as on 14-Jan-2026
Assets :
Work not linked with IM
Bridges on The Basis of AI: