Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 4 | 4 | 4.000 | 0 | 0.000 | 0.000 |
17W320 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : ई फाईल संख्या 27182
TS Amount (lakhs) : 229.91 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
229.91
Resanction Cost :
229.91
Tentative Cost :
229.91
Exp. Upto Last Fy : 184.47
For CFY 2024-2025
Remaining : 45.44
Demand : 45.44
Allotment : 45.44
Exp in CFY : 0.00
Total Up to Date Exp : 184.47
Construction Started
Physical Progress:
At start of FY 2024-2025 : 90 %
Up to Date : 95 %
Sanction on :
1 year 11 months ago
27 Jul 2022
Tentative Completion date:
1 week 5 hours ago
10 Jul 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्यस्थल पर 95 प्रतिशत कार्य पूर्ण शेष कार्य गतिमान। -- as on 27-Jun-2024