Work Profile Report [17W321]
Tenders
Project Activities
alerts
Samples
Administrative Approval Detail : ई फाईल संख्या 36352 लोक निर्माण अनुभाग 2
TS Amount (lakhs) : 283.03 Lacs
Budget Financial Head : NABARD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
294.86
Resanction Cost :
355.95
Tentative Cost :
355.95
Exp. Upto Last Fy :
113.58
For CFY 2025-2026
Remaining :
242.37
Demand :
170.00
Allotment :
25.79
Exp in CFY :
25.79
Total Up to Date Exp :
139.37
Construction Started
Sanction on : 2 years 7 months ago
09 Nov 2022
Physical Progress:
At start of FY 2025-2026 :
38 %
Up to Date :
50 %
Tentative Completion date on : 6 months 2 days from now
30 Dec 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
Overall Excess requirement 61.09 has been counted as tentative cost increased from 294.86 to 355.95 . -- as on 12-Jun-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: