Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5 | 5 | 5 | 0 |
17W321 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : ई फाईल संख्या 36352 लोक निर्माण अनुभाग 2
TS Amount (lakhs) : 283.03 Lacs
Financial Detail
Sanction Cost : 294.86 Lacs
Resanction Cost : 294.86 Lacs
Exp. Upto Last Fy : 25.35 Lacs
For CFY 2024-2025
Remaining : 269.51 Lacs
Demand : 262.50 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.40 Lacs
Total Up to Date Exp : 25.75 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 18 %
Up to Date : 18 %
Sanction on :
1 year 6 months ago
09 Nov 2022
Tentative Completion date:
4 months 2 weeks from now
04 Oct 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
जी1 बिछाने का कार्य एवं जी2 एकत्रीकरण का कार्य प्रगति पर। -- as on 01-Feb-2024
Physical Peramenters