Work Profile Report : 17W368
Tenders
Project Activities
alerts
Samples
Administrative Approval Detail : E-file No. 53625 Lok Nirman Anubhag-2
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : Bridges State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
11.20
Resanction Cost :
11.20
Tentative Cost :
11.20
Exp. Upto Last Fy :
0.10
For CFY 2025-2026
Remaining :
11.10
Demand :
5.76
Allotment :
5.76
Exp in CFY :
5.76
Total Up to Date Exp :
5.86
Phase1 DPR Submitted
Sanction on : 2 years 8 months ago
16 May 2023
Physical Progress:
At start of FY 2025-2026 :
25 %
Up to Date :
95 %
Tentative Completion date on : 5 months 2 weeks from now
31 Jul 2026
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
विस्तृत आगणन आपतियों में प्राप्त है आपतियों का निराकरण कर पुनः अधीक्षण अभियंता तृतीय वृत्त लो0 नि0 वि0 पिथोरागढ़ को प्रेषित किया गया है | -- as on 31-Jan-2026
Assets :
Work not linked with IM
Bridges on The Basis of AI: