Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2 | 2 | 2 | 0 |
17W388 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : E File No. 52192
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
113.63
Resanction Cost :
113.63
Tentative Cost :
113.63
Exp. Upto Last Fy : 8.26
For CFY 2024-2025
Remaining : 105.37
Demand : 105.37
Allotment : 0.00
Exp in CFY : 24.92
Total Up to Date Exp : 33.17
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 35 %
Sanction on :
8 months 2 weeks ago
27 Oct 2023
Tentative Completion date:
4 months 4 weeks from now
15 Dec 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्यस्थल पर डब्ल्यू0बी0 एम0 , जी1 का कार्य पूर्ण, , जी2 व जी3 का कार्य प्रगति पर। -- as on 25-Jun-2024
Physical Peramenters