Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 24.75 | 24.75 | 24.75 | 0 |
17W389 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : --/III(2)/2023-01(प्रा० आ०)/2023
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
114.07
Resanction Cost :
114.07
Tentative Cost :
114.07
Exp. Upto Last Fy : 29.41
For CFY 2024-2025
Remaining : 84.66
Demand : 84.66
Allotment : 40.00
Exp in CFY : 83.78
Total Up to Date Exp : 113.19
Work completed
Physical Progress:
At start of FY 2024-2025 : 25 %
Up to Date : 100 %
Sanction on :
8 months 3 days ago
14 Nov 2023
Tentative Completion date:
4 months 3 days ago
14 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण, दायित्व शेष। -- as on 18-May-2024