Work Profile Report [18W360]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : fजलाfधकारी चम्पावत के पत्राॅक 395/fज0यो0/2018-19 fदनाॅक 20-07-2018
TS Amount (lakhs) : 40 Lacs
Budget Financial Head : SRMD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
40.00
Resanction Cost :
40.00
Tentative Cost :
40.00
Exp. Upto Last Fy :
5.65
For CFY 2024-2025
Remaining :
34.35
Demand :
33.73
Allotment :
33.73
Exp in CFY :
0.00
Total Up to Date Exp :
5.65
Construction Started
Sanction on : 6 years 5 months ago
20 Jul 2018
Physical Progress:
At start of FY 2024-2025 :
10 %
Up to Date :
45 %
Tentative Completion date on :
Yet To Decide
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य प्रगति पर । -- as on 14-Aug-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: