Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3 | 3 | 3.000 | 0 | 0.000 | 0.000 |
No of Bridges | 1 | 1 | 1 | 0 | 0 | 0 |
Span of Bridges [m] | 15 | 15 | 0.000 | 15 | 0.000 | 0.000 |
18W528 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश सं0 1437/।।।(2)/20.54(एम0एल0ए0) /2017 टी0सी0 देहरादून दिनाॅक 05-08-2020
TS Amount (lakhs) : 245.02 Lacs
Financial Detail
Sanction Cost : 245.02 Lacs
Resanction Cost : 245.02 Lacs
Exp. Upto Last Fy : 220.51 Lacs
For CFY 2024-2025
Remaining : 24.51 Lacs
Demand : 0.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 220.51 Lacs
In Maintenance After Completion
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
3 years 9 months ago
05 Aug 2020
Tentative Completion date:
1 month 2 weeks ago
31 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण। नाबार्ड के अन्तर्गत मार्ग पंचवर्षीय अनुरक्षणाधीन है। -- as on 23-Apr-2024