Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 0.75 | 0.75 | 0.000 | 0.75 | 0.750 | 0.750 |
18W605 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश सं0 5971(1)/।।।(2)/21-54(एम0एल0ए0)/2017 टी0सी0-ं।। लोक निर्माण अनुभाग-2 देहरादून, दिनाॅक 09-12-2021
TS Amount (lakhs) : 48.64 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
48.64
Resanction Cost :
48.64
Tentative Cost :
48.64
Exp. Upto Last Fy : 8.77
For CFY 2024-2025
Remaining : 39.87
Demand : 20.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 8.77
Work completed
Physical Progress:
At start of FY 2024-2025 : 40 %
Up to Date : 100 %
Sanction on :
2 years 7 months ago
09 Dec 2021
Tentative Completion date:
1 month 1 week ago
05 Jun 2024
Actual Completion Date:
1 month 1 week ago
05 Jun 2024
Remark
Bottelneck: no issue
कार्य पूर्ण। दायित्व शेष। -- as on 25-Jun-2024