Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5 | 5 | 5.000 | 0 | 0.000 | 0.000 |
18W627 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : ई पत्रावली संख्या . 19207 लोक निर्माण अनुभाग-2 देहरादून: दिनांक 11-10-2022
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
115.78
Resanction Cost :
115.78
Tentative Cost :
115.78
Exp. Upto Last Fy : 100.65
For CFY 2024-2025
Remaining : 15.13
Demand : 15.13
Allotment : 15.13
Exp in CFY : 8.74
Total Up to Date Exp : 109.38
In Maintenance After Completion
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
1 year 9 months ago
11 Oct 2022
Tentative Completion date:
4 months 1 week ago
08 Mar 2024
Actual Completion Date:
4 months 2 days ago
15 Mar 2024
Remark
Bottelneck: no issue
कार्य पूर्ण। नाबार्ड के अन्तर्गत मार्ग पंचवर्षीय अनुरक्षणाधीन है। -- as on 23-Apr-2024
Physical Peramenters