Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3.925 | 3.925 | 2.750 | 1.175 | 1.175 | 0.750 |
18W628 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : ई पत्रावली संख्या . 19329, लोक निर्माण अनुभाग-2 देहरादून: दिनाॅक 10-11-2022
TS Amount (lakhs) : 88.79 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
88.79
Resanction Cost :
88.79
Tentative Cost :
88.79
Exp. Upto Last Fy : 22.82
For CFY 2024-2025
Remaining : 65.97
Demand : 30.00
Allotment : 0.00
Exp in CFY : 24.18
Total Up to Date Exp : 46.99
Construction Started
Physical Progress:
At start of FY 2024-2025 : 60 %
Up to Date : 75 %
Sanction on :
1 year 8 months ago
10 Nov 2022
Tentative Completion date:
1 week 6 days from now
31 Jul 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
3.50 किमी0 पहाड़ कटान का कार्य पूर्ण। अवशेष कार्य प्रगति पर। -- as on 22-May-2024