Work Profile Report [18W629]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : ई पत्रावली संख्या . 19207, लोक निर्माण अनुभाग-2 देहरादूनरू दिनाॅक 14-11-2022
TS Amount (lakhs) : 72.83 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
72.83
Resanction Cost :
72.83
Tentative Cost :
45.00
Saving
27.83
Exp. Upto Last Fy :
0.00
For CFY 2024-2025
Remaining :
72.83
Demand :
50.00
Allotment :
23.62
Exp in CFY :
23.62
Total Up to Date Exp :
23.62
Work completed
Sanction on : 2 years 1 month ago
14 Nov 2022
Physical Progress:
At start of FY 2024-2025 :
30 %
Up to Date :
100 %
Tentative Completion date on : 4 months 3 weeks ago
31 Jul 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
पहाड़ कटान का कार्य पूर्ण। -- as on 24-Oct-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: