Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3 | 3 | 1.000 | 2 | 2.000 | 1.000 |
18W629 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : ई पत्रावली संख्या . 19207, लोक निर्माण अनुभाग-2 देहरादूनरू दिनाॅक 14-11-2022
TS Amount (lakhs) : 72.83 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
72.83
Resanction Cost :
72.83
Tentative Cost :
72.83
Exp. Upto Last Fy : 0.00
For CFY 2024-2025
Remaining : 72.83
Demand : 50.00
Allotment : 0.00
Exp in CFY : 22.16
Total Up to Date Exp : 22.16
Construction Started
Physical Progress:
At start of FY 2024-2025 : 30 %
Up to Date : 70 %
Sanction on :
1 year 8 months ago
14 Nov 2022
Tentative Completion date:
1 week 6 days from now
31 Jul 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
2 किमी0 पहाड़ कटान का कार्य पूर्ण। अवशेष कार्य प्रगति पर। -- as on 22-May-2024
Physical Peramenters