Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.5 | 1.5 | 0.000 | 1.5 | 1.500 | 1.500 |
18W692 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : ई पत्रावली सं0 36717 दि0 28-3-2023
TS Amount (lakhs) : 66.15 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
66.15
Resanction Cost :
66.15
Tentative Cost :
66.15
Exp. Upto Last Fy : 19.21
For CFY 2024-2025
Remaining : 46.94
Demand : 40.00
Allotment : 40.00
Exp in CFY : 15.63
Total Up to Date Exp : 34.84
Work completed
Physical Progress:
At start of FY 2024-2025 : 40 %
Up to Date : 100 %
Sanction on :
1 year 3 months ago
28 Mar 2023
Tentative Completion date:
2 months 3 weeks ago
26 Apr 2024
Actual Completion Date:
1 month 2 weeks ago
02 Jun 2024
Remark
Bottelneck: no issue
कार्य पूर्ण। दायित्व शेष। -- as on 25-Jun-2024
Physical Peramenters