Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 9.3 | 9 | 6.000 | 3 | 3.000 | 3.000 |
18W700 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : पत्रांकः 895/07 याता0-पी0एम0जी0एस0वाई0-नि0 III दिनांकः 16.05.2023
TS Amount (lakhs) : 139.77 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
139.77
Resanction Cost :
139.77
Tentative Cost :
139.77
Exp. Upto Last Fy : 66.26
For CFY 2024-2025
Remaining : 73.51
Demand : 50.00
Allotment : 50.00
Exp in CFY : 0.00
Total Up to Date Exp : 66.26
Work completed
Physical Progress:
At start of FY 2024-2025 : 60 %
Up to Date : 100 %
Sanction on :
1 year 2 months ago
16 May 2023
Tentative Completion date:
2 weeks 1 day ago
02 Jul 2024
Actual Completion Date:
2 weeks 1 day ago
02 Jul 2024
Remark
Bottelneck: no issue
9 किमी पी0सी0 का कार्य पूर्ण। -- as on 02-Jul-2024