Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 8 | 8 | 5.000 | 3 | 3.000 | 3.000 |
18W701 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : पत्रांकः 895/07 याता0-पी0एम0जी0एस0वाई0-नि0 III दिनांकः 16.05.2023
TS Amount (lakhs) : 141.7 Lacs
Financial Detail
Sanction Cost : 141.70 Lacs
Resanction Cost : 141.70 Lacs
Exp. Upto Last Fy : 36.73 Lacs
For CFY 2024-2025
Remaining : 104.97 Lacs
Demand : 80.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 36.73 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 70 %
Up to Date : 90 %
Sanction on :
1 year 3 days ago
16 May 2023
Tentative Completion date:
1 month 1 week from now
30 Jun 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
पी0सी0 का कार्य पूर्ण। अवशेष कार्य प्रगति पर। -- as on 02-May-2024
Physical Peramenters