Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 16 | 16 | 1.000 | 15 | 15.000 | 14.500 |
18W702 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : पत्रांकः 895/07 याता0-पी0एम0जी0एस0वाई0-नि0 III दिनांकः 16.05.2023
TS Amount (lakhs) : 209.8 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
209.80
Resanction Cost :
209.80
Tentative Cost :
209.80
Exp. Upto Last Fy : 35.21
For CFY 2024-2025
Remaining : 174.59
Demand : 100.00
Allotment : 50.00
Exp in CFY : 39.83
Total Up to Date Exp : 75.04
Construction Started
Physical Progress:
At start of FY 2024-2025 : 10 %
Up to Date : 95 %
Sanction on :
1 year 2 months ago
16 May 2023
Tentative Completion date:
5 months 4 days from now
22 Dec 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
15.500 किमी0 पी0सी0 का कार्य पूर्ण। अवशेष कार्य प्रगति पर। -- as on 15-Jul-2024
Physical Peramenters