Work Profile Report [18W702]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : पत्रांकः 895/07 याता0-पी0एम0जी0एस0वाई0-नि0 III दिनांकः 16.05.2023
TS Amount (lakhs) : 209.8 Lacs
Budget Financial Head : Not Available
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
209.80
Resanction Cost :
209.80
Tentative Cost :
209.80
Exp. Upto Last Fy :
203.29
For CFY 2025-2026
Remaining :
6.51
Demand :
0.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
203.29
Work completed
Sanction on : 2 years 1 month ago
16 May 2023
Physical Progress:
At start of FY 2025-2026 :
100 %
Up to Date :
100 %
Tentative Completion date on : 6 months 2 weeks ago
22 Dec 2024
Actual Completion Date : 7 months 3 weeks ago
13 Nov 2024
Physical Linear Components
Remark
कार्य पूर्ण दायित्व शेष। -- as on 04-Dec-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: