Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 19 | 19 | 2.000 | 17 | 17.000 | 11.000 |
18W704 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : पत्रांकः 895/07 याता0-पी0एम0जी0एस0वाई0-नि0 III दिनांकः 16.05.2023
TS Amount (lakhs) : 533.78 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
266.89
Resanction Cost :
266.89
Tentative Cost :
266.89
Exp. Upto Last Fy : 20.00
For CFY 2024-2025
Remaining : 246.89
Demand : 150.00
Allotment : 90.00
Exp in CFY : 35.00
Total Up to Date Exp : 55.00
Construction Started
Physical Progress:
At start of FY 2024-2025 : 15 %
Up to Date : 70 %
Sanction on :
1 year 2 months ago
16 May 2023
Tentative Completion date:
2 weeks 3 days from now
04 Aug 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
13 किमी0 पी0सी0 का कार्य पूर्ण। अवशेष कार्य प्रगति पर। -- as on 13-Jun-2024
Physical Peramenters