Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 19 | 19 | 2.000 | 17 | 17.000 | 0.000 |
18W704 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : पत्रांकः 895/07 याता0-पी0एम0जी0एस0वाई0-नि0 III दिनांकः 16.05.2023
TS Amount (lakhs) : 533.78 Lacs
Financial Detail
Sanction Cost : 266.89 Lacs
Resanction Cost : 266.89 Lacs
Exp. Upto Last Fy : 20.00 Lacs
For CFY 2024-2025
Remaining : 246.89 Lacs
Demand : 150.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 20.00 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 15 %
Up to Date : 15 %
Sanction on :
1 year 3 days ago
16 May 2023
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
2 किमी0 पी0सी0 का कार्य पूर्ण। अवशेष कार्य प्रगति पर। -- as on 04-Apr-2024
Physical Peramenters