Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 4.65 | 4.65 | 0.000 | 4.65 | 4.650 | 4.650 |
18W725 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : ई0 पत्रावली संख्या 48456, लोक निर्माण अनुभाग-2, देहरादून दि0 31-07-2023
TS Amount (lakhs) : 66.7 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
66.70
Resanction Cost :
66.70
Tentative Cost :
66.70
Exp. Upto Last Fy : 0.00
For CFY 2024-2025
Remaining : 66.70
Demand : 50.00
Allotment : 30.00
Exp in CFY : 34.32
Total Up to Date Exp : 34.32
Work completed
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 100 %
Sanction on :
11 months 2 weeks ago
31 Jul 2023
Tentative Completion date:
2 days 5 hours ago
15 Jul 2024
Actual Completion Date:
2 days 5 hours ago
15 Jul 2024
Remark
Bottelneck: no issue
कार्य पूर्ण। -- as on 15-Jul-2024
Physical Peramenters