Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 17 | 17 | 10.000 | 7 | 7.000 | 7.000 |
18W727 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : ई0 पत्रावली संख्या 48456, लोक निर्माण अनुभाग-2, देहरादून दि0 31-07-2023
TS Amount (lakhs) : 262.39 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
272.45
Resanction Cost :
272.45
Tentative Cost :
272.45
Exp. Upto Last Fy : 131.40
For CFY 2024-2025
Remaining : 141.05
Demand : 100.00
Allotment : 100.00
Exp in CFY : 117.26
Total Up to Date Exp : 248.67
Work completed
Physical Progress:
At start of FY 2024-2025 : 70 %
Up to Date : 100 %
Sanction on :
11 months 2 weeks ago
31 Jul 2023
Tentative Completion date:
3 weeks 4 days ago
22 Jun 2024
Actual Completion Date:
3 weeks 4 days ago
22 Jun 2024
Remark
Bottelneck: no issue
कार्य पूर्ण। -- as on 27-Jun-2024
Physical Peramenters