Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 17 | 17 | 10.000 | 7 | 7.000 | 3.000 |
18W727 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : ई0 पत्रावली संख्या 48456, लोक निर्माण अनुभाग-2, देहरादून दि0 31-07-2023
TS Amount (lakhs) : 262.39 Lacs
Financial Detail
Sanction Cost : 272.45 Lacs
Resanction Cost : 272.45 Lacs
Exp. Upto Last Fy : 131.40 Lacs
For CFY 2024-2025
Remaining : 141.05 Lacs
Demand : 100.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 131.40 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 70 %
Up to Date : 75 %
Sanction on :
9 months 2 weeks ago
31 Jul 2023
Tentative Completion date:
1 month 1 week from now
30 Jun 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
13 किमी0 पी0सी0 का कार्य पूर्ण। अवशेष कार्य प्रगति पर। -- as on 02-May-2024
Physical Peramenters