Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 0.5 | 0.5 | 0.000 | 0.5 | 0.500 | 0.000 |
18W732 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : ई0 पत्रावली संख्या- 38109, लोक निर्माण अनुभाग-2 देहरादून, दिनांक 22-09-2023
TS Amount (lakhs) : 45.41 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
45.41
Resanction Cost :
45.41
Tentative Cost :
45.41
Exp. Upto Last Fy : 21.02
For CFY 2024-2025
Remaining : 24.39
Demand : 24.00
Allotment : 20.00
Exp in CFY : 0.00
Total Up to Date Exp : 21.02
Construction Started
Physical Progress:
At start of FY 2024-2025 : 10 %
Up to Date : 60 %
Sanction on :
9 months 3 weeks ago
22 Sep 2023
Tentative Completion date:
1 week 4 hours ago
10 Jul 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
इण्टरलाॅक टाईल लगाने का कार्य प्रगति पर है। -- as on 26-Jun-2024
Physical Peramenters