Work Profile Report [18W788]
Tenders
Aggrements
Project Activities
alerts
Documents
Administrative Approval Detail : शासनादेश सं0 4088/।।।(2)/2023-(प्रा0आ0)/2023 दिनांक 1-11-2023
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : Not Available
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
474.42
Resanction Cost :
474.42
Tentative Cost :
474.42
Exp. Upto Last Fy :
474.40
For CFY 2025-2026
Remaining :
0.02
Demand :
0.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
474.40
Work completed
Sanction on : 1 year 8 months ago
01 Nov 2023
Physical Progress:
At start of FY 2025-2026 :
100 %
Up to Date :
100 %
Tentative Completion date on : 9 months 2 weeks ago
22 Sep 2024
Actual Completion Date : 10 months 1 week ago
30 Aug 2024
Physical Linear Components
Remark
कार्य पूर्ण। -- as on 20-Nov-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: