Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5.5 | 5.5 | 0.000 | 5.5 | 4.000 | 0.000 |
18W807 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासन के ई पत्रावली सं0 19329/55 लोक निर्माण विभाग अनुभाग-2 देहरादून दिनांक 1-2-2024
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
482.88
Resanction Cost :
482.88
Tentative Cost :
482.88
Exp. Upto Last Fy : 0.10
For CFY 2024-2025
Remaining : 482.78
Demand : 200.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 0.10
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 5 %
Sanction on :
5 months 2 weeks ago
01 Feb 2024
Tentative Completion date:
11 months 6 days from now
24 Jun 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
डिफेक्ट कटिंग का कार्य प्रगति पर। -- as on 26-Jun-2024
Physical Peramenters