Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3.65 | 3.65 | 0.000 | 3.65 | 3.650 | 1.000 |
18W840 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : प्रमुख अभियन्ता एवं विभागाध्यक्ष, नियोजन वर्ग उत्तराखण्ड, देहरादून का पत्रांक 388/14याता0 (क)/उ0/2023 दिनांक 15-3-2024
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
58.65
Resanction Cost :
58.65
Tentative Cost :
58.65
Exp. Upto Last Fy : 0.00
For CFY 2024-2025
Remaining : 58.65
Demand : 45.00
Allotment : 0.00
Exp in CFY : 9.94
Total Up to Date Exp : 9.94
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 20 %
Sanction on :
4 months 2 days ago
15 Mar 2024
Tentative Completion date:
2 months 1 week from now
30 Sep 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
1.20 किमी0 पी0 सी0 का कार्य पूर्ण। अवशेष कार्य प्रगति पर। -- as on 02-Jul-2024
Physical Peramenters