Work Profile Report : 19W133

जनपद चम्पावत में चम्पावत-मंच-तामली मोटर मार्ग से मुख्य तोक कारी तक मोटर मार्ग का नव निर्माण (प्रथम चरण)
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Remarks
  • Tenders

    Aggrements

    Project Activities

    alerts

  • Documents
  • Samples

Administrative Approval Detail : शा0स0 3851(1)/।।।(2)/11-64(एम0एल0ए0)/ 2011 दिनांक 07-07-2011

TS Amount (lakhs) : 0 Lacs

Budget Financial Head : State Sector ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

25.20

Resanction Cost :

25.20

Tentative Cost :

25.20

Exp. Upto Last Fy :

22.00

For CFY 2025-2026

Remaining :

3.20

Demand :

0.00

Allotment :

0.00

Exp in CFY :

0.00

Total Up to Date Exp :

22.00

Phase1 DPR Submitted

Sanction on : 14 years 7 months ago

07 Jul 2011

Physical Progress:

At start of FY 2025-2026 :

100 %

Up to Date :

100 %

Tentative Completion date on : 3 months 1 week from now

20 May 2026

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2025-2026
Remaining
Target
Achievement
Road [Km]
2
2
2
-

Remark

view all

प्रथम चरण का कार्य पूर्ण। स्वीकृति उपरान्त द्वितीय चरण स्टेज-1 का कार्य पूर्ण, स्टेज-।। की डी0पी0आर0 प्रेषित की जानी है। प्रथम चरण के अन्तर्गत मुआवजे का वितरण किया जा चुका है ,स्टेज-2 की डीपीआर गठित कर ई-डीपीआर आई डी- 8117 के माध्यम से उच्चाधिकारियों को प्रेषित। आपत्तियों में प्राप्त। उक्त मार्ग में डामरीकरण हेतु मा0 मुख्यमंत्री महोदय द्वारा घोषणा की गई है। घोषणा का शासनादेश प्राप्त होने के उपरान्त आंगणन पुनः प्रेषित कर दिया जायेगा। -- as on 04-Feb-2026

Rating : 100

No Forest Case in The Work

No Hindrance / Bottleneck

Assets :

Work not linked with IM

Bridges on The Basis of AI: