Work Profile Report [19W529]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : 1311/।।।(2)/19-55(एम0एल0ए0)/2017 टी0सी0-1 दिनांक 07 मार्च, 2019
TS Amount (lakhs) : 144.88 Lacs
Budget Financial Head : NABARD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
144.88
Resanction Cost :
144.88
Tentative Cost :
144.88
Exp. Upto Last Fy :
138.60
For CFY 2024-2025
Remaining :
6.28
Demand :
7.07
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
138.60
In Maintenance After Completion
Sanction on : 5 years 8 months ago
07 Mar 2019
Physical Progress:
At start of FY 2024-2025 :
100 %
Up to Date :
100 %
Tentative Completion date on : 2 years 7 months ago
31 Mar 2022
Actual Completion Date : 2 years 8 months ago
02 Mar 2022
Physical Linear Components
Remark
कार्य पूर्ण, दायित्व शेष। अनुरक्षण कार्यो हेतु निविदा आमंत्रित। -- as on 04-Oct-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: