Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
No of Bridges | 1 | 1 | 0 | 1 | 1 | 0 |
Span of Bridges [m] | 125 | 125 | 0.000 | 125 | 125.000 | 0.000 |
19W652 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : E letter no.-31110, date-27-07-2022
TS Amount (lakhs) : 1377.14 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
1377.14
Resanction Cost :
1377.14
Tentative Cost :
1377.14
Exp. Upto Last Fy : 457.52
For CFY 2024-2025
Remaining : 919.62
Demand : 919.62
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 457.52
Construction Started
Physical Progress:
At start of FY 2024-2025 : 60 %
Up to Date : 80 %
Sanction on :
1 year 11 months ago
27 Jul 2022
Tentative Completion date:
2 months 1 week from now
30 Sep 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
अबेटमेंट एवं पियर्स का कार्य पूर्ण स्लैब हेतु बीम कंक्रीटिंग का कार्य पूर्ण स्लैब की शटरिंग व रैनफोर्स्मेंट का प्रगति पर -- as on 13-Jul-2024