Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
No of Bridges | 1 | 1 | 0 | 1 | 1 | 0 |
Span of Bridges [m] | 125 | 125 | 0.000 | 125 | 125.000 | 0.000 |
19W652 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : E letter no.-31110, date-27-07-2022
TS Amount (lakhs) : 1377.14 Lacs
Financial Detail
Sanction Cost : 1,377.14 Lacs
Resanction Cost : 1,377.14 Lacs
Exp. Upto Last Fy : 457.52 Lacs
For CFY 2024-2025
Remaining : 919.62 Lacs
Demand : 919.62 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 457.52 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 60 %
Up to Date : 63 %
Sanction on :
1 year 9 months ago
27 Jul 2022
Tentative Completion date:
7 months 1 week from now
31 Dec 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
अबेटमेंट का कार्य पूर्ण स्लैब शटरिंग का कार्य प्रगति पर -- as on 02-May-2024
Physical Peramenters