Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 24.85 | 24.85 | 0.800 | 24.05 | 24.050 | 0.000 |
19W671 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : E-File No. 35871 Dated : 15-12-2022
TS Amount (lakhs) : 1690.28 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
1783.33
Resanction Cost :
1783.33
Tentative Cost :
1783.33
Exp. Upto Last Fy : 933.85
For CFY 2024-2025
Remaining : 849.48
Demand : 849.48
Allotment : 0.00
Exp in CFY : 485.28
Total Up to Date Exp : 1,419.13
Construction Started
Physical Progress:
At start of FY 2024-2025 : 70 %
Up to Date : 95 %
Sanction on :
1 year 7 months ago
15 Dec 2022
Tentative Completion date:
3 months 3 weeks from now
08 Nov 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
PC कार्य पूर्ण नाली निर्माण एवं रोड फर्निशिंग का कार्य प्रगति पर है -- as on 29-Jun-2024
Physical Peramenters