Work Profile Report [19W685]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : E file no-35984
TS Amount (lakhs) : 103.46 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
103.46
Resanction Cost :
103.46
Tentative Cost :
103.46
Exp. Upto Last Fy :
14.90
For CFY 2024-2025
Remaining :
88.56
Demand :
70.00
Allotment :
57.47
Exp in CFY :
57.47
Total Up to Date Exp :
72.38
Construction Started
Sanction on : 1 year 7 months ago
31 Mar 2023
Physical Progress:
At start of FY 2024-2025 :
2 %
Up to Date :
60 %
Tentative Completion date on : 1 week 16 hours ago
16 Nov 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य प्रगति पर। -- as on 28-Oct-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand