Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 7.7 | 7.7 | 5.000 | 2.7 | 2.700 | 0.000 |
19W686 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : कार्यालय प्रमुख अभियन्ता (विभागाध्यक्ष) लोक निर्माण विभाग उत्तराखण्ड देहरादून के पत्रांक 895/07 याता0-पी0एम0जी0एस0वाई0-नि0।।। दिनांक-16-05-2023 द्वारा स्वीकृत।
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
143.33
Resanction Cost :
143.33
Tentative Cost :
143.33
Exp. Upto Last Fy : 98.28
For CFY 2024-2025
Remaining : 45.05
Demand : 45.05
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 98.28
Work completed
Physical Progress:
At start of FY 2024-2025 : 85 %
Up to Date : 100 %
Sanction on :
1 year 2 months ago
16 May 2023
Tentative Completion date:
2 months 4 weeks ago
18 Apr 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण दायित्व शेष (04/2024) -- as on 02-May-2024
Physical Peramenters