Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 11.75 | 11.75 | 10.000 | 1.75 | 1.750 | 0.000 |
19W689 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : प्रमुख अभियन्ता (विभागाध्यक्ष) लोक निर्माण विभाग उत्तराखण्ड देहरादून के पत्रांक 895/07 याता0-पी0एम0जी0एस0वाई0-नि0।।। दिनांक-16-05-2023
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 359.93 Lacs
Resanction Cost : 359.93 Lacs
Exp. Upto Last Fy : 180.04 Lacs
For CFY 2024-2025
Remaining : 179.89 Lacs
Demand : 179.89 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 180.04 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 70 %
Up to Date : 95 %
Sanction on :
1 year 3 days ago
16 May 2023
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रगति पर। -- as on 18-Nov-2023