Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2 | 2 | 2.000 | 0 | 0.000 | 0.000 |
19W691 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : कार्यालय प्रमुख अभियन्ता (विभागाध्यक्ष) लोक निर्माण विभाग उत्तराखण्ड देहरादून के पत्रांक 895/07 याता0-पी0एम0जी0एस0वाई0-नि0।।। दिनांक-16-05-2023
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 62.82 Lacs
Resanction Cost : 62.82 Lacs
Exp. Upto Last Fy : 53.24 Lacs
For CFY 2024-2025
Remaining : 9.58 Lacs
Demand : 9.58 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 53.24 Lacs
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
1 year 3 days ago
16 May 2023
Tentative Completion date:
3 months 2 weeks ago
31 Jan 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण, दायित्व शेष। -- as on 04-Feb-2024
Physical Peramenters