Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 7.5 | 7.5 | 3.500 | 4 | 0.000 | 0.000 |
19W692 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : कार्यालय प्रमुख अभियन्ता (विभागाध्यक्ष) लोक निर्माण विभाग उत्तराखण्ड देहरादून के पत्रांक 895/07 याता0-पी0एम0जी0एस0वाई0-नि0।।। दिनांक-16-05-2023
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 57.83 Lacs
Resanction Cost : 57.83 Lacs
Exp. Upto Last Fy : 41.81 Lacs
For CFY 2024-2025
Remaining : 16.02 Lacs
Demand : 7.50 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 41.81 Lacs
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
1 year 3 days ago
16 May 2023
Tentative Completion date:
3 months 2 weeks ago
31 Jan 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण, दायित्व शेष। -- as on 04-Feb-2024