Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 6.5 | 6.5 | 6.500 | 0 | 0.000 | 0.000 |
19W696 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासन की ई पत्रावली संख्या 48456 दिनांक 31 जुलाई, 2023
TS Amount (lakhs) : 115.67 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
115.67
Resanction Cost :
115.67
Tentative Cost :
115.67
Exp. Upto Last Fy : 84.44
For CFY 2024-2025
Remaining : 31.23
Demand : 31.23
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 84.44
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
11 months 2 weeks ago
31 Jul 2023
Tentative Completion date:
5 months 2 weeks ago
31 Jan 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण, दायित्व शेष। -- as on 04-Feb-2024