Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.8 | 1.8 | 0.500 | 1.3 | 1.300 | 0.000 |
19W719 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : E- File No. 31012 Dated : 07-082023
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
208.98
Resanction Cost :
208.98
Tentative Cost :
208.98
Exp. Upto Last Fy : 34.87
For CFY 2024-2025
Remaining : 174.11
Demand : 174.11
Allotment : 0.00
Exp in CFY : 86.39
Total Up to Date Exp : 121.27
Construction Started
Physical Progress:
At start of FY 2024-2025 : 10 %
Up to Date : 70 %
Sanction on :
11 months 1 week ago
07 Aug 2023
Tentative Completion date:
6 months 5 days from now
23 Jan 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
टॉप कोट तक का कार्य पूर्ण 1.400 किमी में इंटरलॉकिंग टाइल का कार्य पूर्ण सेष कार्य प्रगति पर है -- as on 29-Jun-2024
Physical Peramenters