Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 58 | 58 | 0.000 | 58 | 23.200 | 0.000 |
19W746 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 256/III(3)/2024-01(C.R.I.F.)2022 Dated : 29-02-2024
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 2,457.00 Lacs
Resanction Cost : 2,393.71 Lacs
Exp. Upto Last Fy : 165.13 Lacs
For CFY 2024-2025
Remaining : 2,228.58 Lacs
Demand : 792.35 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 165.13 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 5 %
Up to Date : 5 %
Sanction on :
2 months 2 weeks ago
29 Feb 2024
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रगति पर है -- as on 31-Mar-2024
Physical Peramenters