Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 58 | 58 | 0.000 | 58 | 23.200 | 0.000 |
19W746 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 256/III(3)/2024-01(C.R.I.F.)2022 Dated : 29-02-2024
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
2457.00
Resanction Cost :
2393.71
Tentative Cost :
2393.71
Exp. Upto Last Fy : 165.13
For CFY 2024-2025
Remaining : 2,228.58
Demand : 792.35
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 165.13
Construction Started
Physical Progress:
At start of FY 2024-2025 : 5 %
Up to Date : 7 %
Sanction on :
4 months 2 weeks ago
29 Feb 2024
Tentative Completion date:
10 months 3 weeks from now
14 Jun 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
सिविल कार्य (दिवार स्कपर आदि ) का कार्य प्रगति पर है -- as on 29-Jun-2024
Physical Peramenters