Work Profile Report [19W759]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : Uk. Gov. E-File No. 3108 Dated : 14-03-2024
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
35.15
Resanction Cost :
35.15
Tentative Cost :
35.15
Exp. Upto Last Fy :
0.00
For CFY 2024-2025
Remaining :
35.15
Demand :
35.15
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
0.00
Construction Started
Sanction on : 9 months 1 week ago
14 Mar 2024
Physical Progress:
At start of FY 2024-2025 :
0 %
Up to Date :
40 %
Tentative Completion date on : 1 month 2 weeks from now
09 Feb 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
स्कप्पर और दीवार निर्माण , जीएसबी का कार्य पूर्ण। शेष कार्य प्रगति पर -- as on 04-Dec-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: