Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 150 | 150 | 0.000 | 150 | 150.000 | 0.000 |
19W760 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश संख्या 272 / III (2)/2024-01 (प्रा0 आ0 )2023 दिनांक 31/01/2024
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
1044.66
Resanction Cost :
1044.66
Tentative Cost :
1044.66
Exp. Upto Last Fy : 59.64
For CFY 2024-2025
Remaining : 985.02
Demand : 985.02
Allotment : 0.00
Exp in CFY : 386.57
Total Up to Date Exp : 446.22
Construction Started
Physical Progress:
At start of FY 2024-2025 : 5 %
Up to Date : 70 %
Sanction on :
5 months 2 weeks ago
31 Jan 2024
Tentative Completion date:
1 month 4 weeks from now
15 Sep 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रगति पर है -- as on 18-Mar-2024
Physical Peramenters