Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 17 | 13 | 13 | 0 |
1W17 :
Administrative Approval Detail : पूर्व शा0स0 2490/।।।-2 /08-61(प्रा0आ0)/07 दिनांक 25.07.08 एवं (नाम परिवर्तन) शा0 सं0 4224/।।।(2)/14-61 (प्रा0आ0)/2017 दिनांक 08.08.2017
TS Amount (lakhs) : 447.84 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
595.00
Resanction Cost :
595.00
Tentative Cost :
595.00
Exp. Upto Last Fy : 514.76
For CFY 2024-2025
Remaining : 80.24
Demand : 15.00
Allotment : 5.50
Exp in CFY : 0.00
Total Up to Date Exp : 514.76
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
6 years 11 months ago
08 Aug 2017
Tentative Completion date:
1 year 5 months ago
01 Feb 2023
Actual Completion Date:
1 year 5 months ago
01 Feb 2023
Remark
Forest Status 12: AIP DM
Bottelneck: no issue
कार्य पूर्ण माह 04/2023 दायित्व शेष। -- as on 12-Sep-2023
Physical Peramenters