Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2 | 2 | 2 | 0 | ||
No of Bridges | 1 | 1 | 1 | 0 | ||
Span of Bridges [m] | 15 | 15 | 15 | 0 |
1W174 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 6581/।।। (2)/11-49 (एम0एल0ए0)/2010 दि0 04.03.2011
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
26.25
Resanction Cost :
26.25
Tentative Cost :
26.25
Exp. Upto Last Fy : 7.56
For CFY 2024-2025
Remaining : 18.69
Demand : 5.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 7.56
Survey work done
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
13 years 4 months ago
04 Mar 2011
Tentative Completion date:
2 years 3 months ago
31 Mar 2022
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 12: AIP DM
Bottelneck: no issue
दिनांक 09.08.2021 द्वारा सैद्धान्तिक स्वीकृति प्राप्त। एन0पी0बी0 की धनराशि जमा करने की कार्यवाही गतिमान। -- as on 07-Aug-2023
Physical Peramenters