Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 10 | 10 | 10 | 0 | ||
No of Bridges | 1 | 1 | 1 | 0 | ||
Span of Bridges [m] | 24 | 24 | 24 | 0 |
1W233 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : श्शासनादेश संख्याः- 767(1)/।।।(2)/13-48 (प्रा0आ0)/2012 दिनांक 01 फरवरी, 2013
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
127.68
Resanction Cost :
127.68
Tentative Cost :
127.68
Exp. Upto Last Fy : 1.89
For CFY 2024-2025
Remaining : 125.79
Demand : 0.50
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 1.89
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
11 years 5 months ago
01 Feb 2013
Tentative Completion date:
2 years 3 months ago
31 Mar 2022
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 03: DM
Bottelneck: no issue
सी0ए0 हेतु भूमि की आवश्यकता है। भूमि का मांग पत्र प्रभागीय वनाधिकारी को प्रेषित। -- as on 30-Jun-2023
Physical Peramenters